- City Services
- Engineering
- Engineering Projects
- Big Eddy Water System - Phase 1
Work completed included replacement of the Big Eddy water main, minor pump house improvements, trench-less replacement work for the two water mains, leading to and from the reservoir.
Work commenced in late April 2017 and was completed in Fall 2017.
Phase 2 will begin construction in 2018 once the contract has been awarded.
Crews are installing services by directional drilling on Big Eddy Road.